Missouri prevailing wage rates and rules

Missouri's prevailing wage law (RSMo 290.210 to 290.340) covers construction of public works over $75,000. The Division of Labor Standards sets the rates each year in an Annual Wage Order, contractors send certified payroll to the public body every month, and a notarized affidavit is filed before final payment.

Updated November 3, 2026 · Sources: RSMo 290.210–290.340, 8 CSR 30-3 and the Missouri Department of Labor and Industrial Relations

Missouri prevailing wage at a glance

TopicMissouri rule
LawRSMo 290.210 to 290.340, last reworked by 2018 legislation (H.B. 1729), effective August 28, 2018; rules in 8 CSR 30-3
Administered byDepartment of Labor and Industrial Relations, Division of Labor Standards
ThresholdNot covered when the engineer's estimate or accepted bid is $75,000 or less
RatesAnnual Wage Order No. 33, in effect since May 29, 2026, by county; General Wage Order No. 70 for Highway Commission projects
Certified payrollMonthly, to the contracting public body; records kept one year after completion
Close-outNotarized affidavit of compliance (form PW-4) before final payment
Penalties$100 per worker per day underpaid, double back wages in worker lawsuits, fines, one-year debarment after a conviction

Which projects pay prevailing wage in Missouri

"Public works" means "all fixed works constructed for public use or benefit or paid for wholly or in part out of public funds" (RSMo 290.210). The law covers workers "engaged in the construction of public works, exclusive of maintenance work" (RSMo 290.230).

  • $75,000 threshold: the law does not apply where the engineer's estimate or accepted bid for the total project cost "is in the amount of seventy-five thousand dollars or less". The Division puts it as projects "valued over $75,000" (Division of Labor Standards).
  • No splitting: a public body "shall not divide a project into multiple contracts for the purpose of lowering the total project cost". If a change order takes a project over $75,000, the wage provisions apply to the amount above $75,000.
  • Construction means "construction, reconstruction, improvement, enlargement, alteration, painting and decorating, or major repair". Maintenance, "the repair, but not the replacement, of existing facilities" without changing their size, type or extent, is not covered. Nor is work for or by a drainage or levee district.
  • On-site workers: the law covers workers directly employed by contractors or subcontractors in actual construction work on the site, and not volunteers who agree in writing to work without pay.

Missouri prevailing wage rates: how much, and where to find them

It depends on the occupational title and the county. "Annual Wage Order No.33 is now final and in effect as of 2026-05-29", and its rates are looked up by county on the Division's prevailing wage lookup, on Building Construction and Heavy Construction rate sheets. Missouri State Highway and Transportation Commission projects use a separate order: "General Wage Order No. 70 is now final and in effect as of July 1, 2026" (Division of Labor Standards).

  • How rates are set since 2018: the prevailing wage for an occupational title is "the weighted average wage for that occupational title" from contractors' reported hours. Where fewer than 1,000 hours are reported, the "public works contracting minimum wage" applies instead: "one hundred twenty percent of the average hourly wage in a particular locality" (RSMo 290.257).
  • Timing: the initial determination is filed by March 10 each year, objections are due within 30 days, and the final annual order is made by July 1.
  • Which rates apply: the public body attaches the rates to the bid specifications, and "The wage rates attached to, and made a part of, the call for bids for a contract shall remain in effect" "for the duration of that particular contract" (8 CSR 30-3.010). The Division's advice: "Contact the public body involved in the project for an official copy of the prevailing wage rates."
  • Overtime and holidays: 1.5 times the prevailing rate for work over 10 hours in a day or over 40 hours in a calendar week, and twice the rate on Sundays and seven listed holidays (RSMo 290.230).

Certified payroll in Missouri

"Each month the successful bid contractors shall submit certified copies of their current payrolls" "to the contracting public body" (8 CSR 30-3.010). Payrolls are recorded by occupational title and type of worker (journeyman, entry-level worker or federally registered apprentice) and show each worker's "name and address", "rate of pay, daily and weekly number of hours worked", "deduction made, and actual wages paid".

  • Form: the Division's LS-57 Contractors Payroll Form "may be used by contractors throughout the project"; it is not required.
  • Records: each contractor keeps full records of every worker's name, occupation, hours and actual wages "for the period of one year following the completion of the public work", open to the public body and the Department (RSMo 290.290).

Before you sign your Missouri certified payroll

Upload the payroll report your payroll system already exports. PrevailReady checks each worker's hours and pay against the rates you enter and flags underpayments before you sign. It doesn't fill in the LS-57 payroll form; it makes sure the numbers you enter there are right. Your first weekly report is free, no card needed.

The PW-4 affidavit before final payment

On completion and before final payment, each contractor and subcontractor files an affidavit of compliance with the contracting public body, and "no public body shall be authorized to make final payment until such affidavit is filed" (RSMo 290.290). The Division's form is PW-4, "Affidavit: Compliance with the Prevailing Wage Law", signed by a company officer and notarized; public bodies also send copies to the Division.

Apprentices and entry-level workers

"Employers may use entry-level workers and federally registered apprentices for on-the-job training periods." Their rate is "fifty percent of the applicable wage rate" for a journeyman in the same occupational title and county, and "The combined total of entry-level workers and federally registered apprentices shall not exceed a one-to-one ratio" with journeymen on the project (RSMo 290.235).

Posting and safety training

Each contractor and subcontractor posts the rates "in a prominent and easily accessible place at the site" (RSMo 290.265); where there is no field office, such as on road or pipeline work, the rule allows posting at the contractor's local office with a copy for any worker who asks (8 CSR 30-3.050). A related law requires a ten-hour OSHA construction safety program for on-site employees on public works, completed within 60 days of starting work (RSMo 292.675).

Penalties

  • Per-worker penalty: the contractor forfeits to the public body "one hundred dollars for each worker employed, for each calendar day, or portion thereof" a worker is underpaid; it is not due until 45 days after the notice (RSMo 290.250).
  • Worker lawsuits: a worker has "a right of action for double whatever difference there may be", plus a reasonable attorney's fee (RSMo 290.300).
  • Criminal: a willful violation is punishable "by a fine not exceeding five hundred dollars" "or by imprisonment not exceeding six months, or by both", and each day is a separate offense (RSMo 290.340).
  • Debarment: contractors convicted under the law are barred from public works contracts "for a period of one year from the date of the first conviction" (RSMo 290.330).

How PrevailReady helps

PrevailReady reads the payroll report and timesheet you already export and checks every worker against the Annual Wage Order rates you enter, so the monthly payroll you certify matches them. It builds the federal WH-347 and the New York, California, New Jersey and Illinois files; it does not fill in the LS-57 or PW-4.

Frequently asked questions

What is the Missouri prevailing wage threshold?

Projects whose engineer's estimate or accepted bid for the total project cost is $75,000 or less are exempt, so the law covers projects over $75,000. Public bodies may not split a project to get under it.

How often is certified payroll due in Missouri?

Monthly. Contractors submit certified copies of their current payrolls to the contracting public body each month, and keep payroll records for one year after the work is completed.

Where do I find current Missouri prevailing wage rates?

On the Division of Labor Standards' Annual Wage Order lookup, by county; Annual Wage Order No. 33 has been in effect since May 29, 2026. Highway Commission projects use General Wage Order No. 70. The rates in your bid specifications apply for the whole contract.

What are the overtime rules on Missouri prevailing wage jobs?

Time and a half for work over 10 hours in a day or 40 hours in a calendar week, and double time on Sundays and the seven listed holidays.

Can apprentices be paid less in Missouri?

Yes. Federally registered apprentices and entry-level workers are paid 50% of the journeyman rate for their occupational title and county, and together they may not exceed a one-to-one ratio with journeymen on the project.