Connecticut prevailing wage rates and rules

Connecticut General Statutes section 31-53 requires prevailing wages on public works of $1,000,000 or more for new construction and $100,000 or more for remodeling and repair. The Labor Commissioner sets the rates, contractors pay each July 1 increase for the life of the contract, and certified payroll goes to the contracting agency every month.

Updated November 3, 2026 · Sources: C.G.S. §§31-53 to 31-55a (2026 Supplement) and the Connecticut Department of Labor

Connecticut prevailing wage at a glance

TopicConnecticut rule
LawC.G.S. §31-53, with §§31-53a to 31-53d, 31-54, 31-55 and 31-55a
Administered byLabor Commissioner; CTDOL Wage and Workplace Standards Division, Wethersfield
ThresholdsNew construction $1,000,000 or more; remodeling, alteration or repair $100,000 or more
RatesProject schedule issued to the contracting agency before bidding; adjusted every July 1 for the life of the contract
Certified payrollMonthly, to the contracting agency, with a signed statement of compliance; a public record
Safety trainingOSHA 10-hour course for private workers on public works contracts entered into on or after July 1, 2009
PenaltiesUp to $5,000 per offense, debarment up to three years, a class D felony for a knowingly false payroll

Which projects pay prevailing wage in Connecticut

Section 31-53 covers each contract for "the construction, remodeling, refinishing, refurbishing" and similar work on "any public works project by the state or any of its agents, or by any political subdivision of the state or any of its agents", at "a rate equal to the rate customary or prevailing for the same work in the same trade or occupation" "in the town in which such public works project is being constructed" (C.G.S. Chapter 557, 2026 Supplement).

Type of projectCovered at
New construction (combined total cost or total bond authorization)$1,000,000 or more
Remodeling, refinishing, refurbishing, rehabilitation, alteration or repair (all contractors' work combined)$100,000 or more

The statute exempts projects "less than one million dollars" and "less than one hundred thousand dollars" (§31-53(h)), so a project at exactly those amounts is covered.

  • DECD-funded projects: when the Department of Economic and Community Development gives a business organization financial assistance "totaling one million dollars or more", the construction contract must carry a prevailing wage clause (§31-53c).
  • Off-site custom fabrication: since July 1, 2025, §31-53(a) also covers "each contract for off-site custom fabrication" for a public works project: systems fabricated in Connecticut specifically for that project, but not "stock shelf items or readily available" materials.

Connecticut prevailing wage rates: how much, and where to find them

It depends on the town and the trade. "The Labor Commissioner shall determine the prevailing rate of wages on an hourly basis" (§31-53(e)), as an hourly rate plus an hourly benefit amount.

  • The project schedule: the contracting agency contacts the Labor Commissioner at least ten but not more than twenty days before bids are advertised, and puts the rates in the proposal. CTDOL issues schedules "project specific ONLY to the Contracting Agency or Agent", and they "MUST be included in the Bid Documents/Bid Specifications at the time the project is advertised for Bid" (CTDOL). Contractors get them from the bid package.
  • July 1 adjustments: contractors "shall contact the Labor Commissioner on or before July first of each year, for the duration of such contract" and make the adjustments "effective each July first" (§31-55a). CTDOL: "Each contractor shall pay the annual adjusted prevailing wage rate that is in effect each July 1st", and since July 1, 2025 "all prevailing wage projects are subject to the annual July 1 rate adjustment."
  • Where the annual rates are: CTDOL's prevailing wage page posts the July 1, 2026 Building, Heavy/Highway and Residential rates, listed by county, town and classification. CTDOL notes that "Rates are subject to change throughout the year."

Certified payroll in Connecticut

Each employer must "submit monthly to the contracting agency" a certified payroll that is "a complete copy of such records", by "mail, electronic mail or other method accepted by such agency", and "the certified payroll shall be considered a public record" (§31-53(f)). CTDOL: "Contractors must submit Certified Payrolls with a statement of compliance monthly to the contracting agency."

  • The statement: the signer certifies that the records are correct, that the employer has complied with §31-53, and that each worker is covered by workers' compensation insurance.
  • Form: CTDOL's "Payroll Certification for Public Works Projects" (WWS-CPI) is laid out as a weekly payroll and can be completed online (CTDOL).
  • Who goes on it: the hours and wages of all persons who perform work on site, regardless of ownership or contractual relationship.
  • False payroll: "filing a certified payroll which the employer knows to be false is a class D felony", with a fine of up to $5,000, up to five years in prison, or both.

Before you sign your Connecticut certified payroll

Upload the payroll report your payroll system already exports. PrevailReady checks each worker's hours and pay against the rates you enter and flags underpayments before you sign. It doesn't fill in CTDOL's payroll certification; it makes sure the numbers you enter there are right. Your first weekly report is free, no card needed.

OSHA 10-hour training

Private workers on public works contracts entered into on or after July 1, 2009 must complete a ten-hour OSHA construction safety course (C.G.S. §31-53b). A completion card issued more than five years before the project starts does not count, and a copy of each worker's card is attached to the first certified payroll on which the worker appears. A worker without proof may work up to fourteen consecutive calendar days and is then subject to removal (CTDOL bulletin).

Apprentices and posting

Apprentices must be "duly registered under the Commissioner of Labor's regulations", may be paid a percentage of the journeyman base rate plus the full fringe rate, and need at least "one full-time journeyperson instructing and supervising" each apprentice (CTDOL rate schedule information). Contractors must "post in a prominent place the prevailing wages as determined by the Labor Commissioner" (CTDOL poster, citing §31-55).

Penalties

  • Underpayment: a contractor who knowingly or willfully fails to pay the rate "shall be issued a citation and may be fined five thousand dollars for each offense"; the state or town may withhold payment or terminate the contract (§31-53(b)).
  • Debarment referral: the Commissioner "shall refer for debarment" contractors whose settlements over the preceding rolling three-year period exceed $50,000 in back wages or fringe benefits, or $50,000 in penalties.
  • Debarment: up to three years; a debarred firm doing covered work owes $1,000 for each day (§31-53a). CTDOL publishes debarment lists.
  • DECD projects: $2,500 to $5,000 per offense and disqualification from DECD-assisted bids (§31-53c).
  • Since October 1, 2026: after a stop work order, the Comptroller may withhold payment from a contractor that stays out of compliance (Public Act 26-17).

How PrevailReady helps

PrevailReady reads the payroll report and timesheet you already export and checks every worker against the rates you enter, including each July 1 adjustment, so the payroll you certify matches CTDOL's schedule. It builds the federal WH-347 and the New York, California, New Jersey and Illinois files; it does not fill in CTDOL's payroll certification form.

Frequently asked questions

What is the Connecticut prevailing wage threshold?

$1,000,000 or more for new construction, and $100,000 or more for remodeling, refinishing, refurbishing, rehabilitation, alteration or repair. Projects below those amounts are exempt.

How often is certified payroll due in Connecticut?

Monthly, to the contracting agency, with a signed statement of compliance. Certified payrolls are public records, and knowingly filing a false one is a class D felony.

Do I have to pay the July 1 rate increase on a Connecticut project that started earlier?

Yes. Contractors must contact the Labor Commissioner by July 1 each year for the duration of the contract and pay the adjusted rates from July 1. Since July 1, 2025 this applies to all prevailing wage projects.

Is OSHA 10 required on Connecticut prevailing wage jobs?

Yes, for private workers on public works contracts entered into on or after July 1, 2009. A copy of each worker's card goes with the first certified payroll the worker appears on, and cards more than five years old do not count.

Where do I find Connecticut prevailing wage rates?

The project's schedule is in the bid documents, issued by CTDOL to the contracting agency. The annual July 1 adjusted rates are on CTDOL's prevailing wage page, listed by county, town and classification.